Issuance of Building Permit

ISSUANCE OF BUILDING PERMIT

A BUILDING Permit is required prior to the construction, erection, alteration, major repair, or renovation or conversion of any building/structure owned by government of private entities.

The permit becomes null and void if work does not commence within one year from the date of such permit, or if the building or work is suspended or abandoned at any time after it has been commenced for a period of 120 days.

Office or Division: Office of the Municipal Engineering


Classification:  Medium

Types of Transaction:  G2B- Government to Owners

                                       

Who may avail: Building Owners


PROCESS

STEP 1

SECURE APPLICATION FORM 

Fees to be Paid: None

Processing Time :10 minutes
Person Responsible:
Engr II, Engineering Assistant 

STEP 1.1

SUBMIT REQUIREMENTS

AGENCY ACTION
Verifies and check the  documents submitted.

Fees to be Paid: None

Processing Time :25 minutes
Person Responsible:
Engr II, Engineering Assistant 

Municipal Engineer

AGENCY ACTION
Validate the completeness of the requirement. 

Fees to be Paid: None
Person Responsible:
Engr II, Engineering Assistant 

Municipal Engineer

AGENCY ACTION
Evaluates plans as to Structural, Architectural, Electrical, Mechanical, Sanitary/Plumbing for assessment.

Fees to be Paid: None
Person Responsible:
Engr II, Engineering Assistant 

Municipal Engineer

AGENCY ACTION
Issues order of payment.

Fees to be Paid: None
Person Responsible:
Engr II, Engineering Assistant 

Municipal Engineer

STEP 2

PAYS ORDER OF PAYMENT

AGENCY ACTION
Call the Applicant

Fees to be Paid: None

Processing Time :15 minutes
Person Responsible:
MTO Staff and Receiving Counter 

AGENCY ACTION
Get the receipt

Fees to be Paid: 

NBC Building Permit fees

Electrical Permit Fees

Plumbing Permit Fees

Processing Time :15 minutes


Person Responsible:
MTO Staff and Receiving Counter 

STEP 3

ENDORSEMENT FOR FIRE SAFETY INSPECTION

AGENCY ACTION
Issue Certificate of Final Electrical Inspection 

Fees to be Paid: None

Processing Time :5 minutes
Person Responsible:
Engr II, Engineering Assistant 

STEP 4

ISSUANCE OF APPLICATION PERMIT

AGENCY ACTION
Issue Building permit, Electrical, and Plumbing Permit

Fees to be Paid: None

Processing Time :5 minutes
Person Responsible:
Engr II, Engineering Assistant 

TOTAL:

Fees to be Paid: Application for Electrical Permit                                         Processing Time: 40 minutes